• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • About
    • Letter to the Editor
    • Newsstand Locations
    • Contact Us
  • Classifieds
    • View Classifieds Online
    • Classified Rates
  • Advertise
  • Subscribe

Times-Herald and Sunday Times Newspapers

  • Home
  • News
  • Editorial
  • Police Blotter
  • Tempo
  • Lifestyle
    • Bridal
    • Food
    • Home Works
    • Home Improvement
    • Home & Lifestyle
    • Lawn & Garden
    • Savvy Senior
    • Sports
  • Special Sections
    • Chamber Chatter
    • Higher Education
    • Homecoming

New city art center renovation enters cleanup, fixup phase

September 5, 2009 By Times-Herald Newspapers Leave a Comment

By SUE SUCHYTA

Sunday Times Newspapers

    WYANDOTTE – Renovations to transform the former Masonic Temple into an art center are well under way.

    The art center committee met Aug. 3 to review the project budget and work estimates.

    City Engineer Mark Kowalewski said the elevator shaft is complete, and that an elevator should be installed by Sept. 30.

    The sprinkler system bid came in lower than expected because the good water pressure in the area precludes the need for an additional pump. However, the bid for the front steps came in higher than originally estimated.

    The City Council, on the recommendation of Kowalewski and Todd Drysdale, director of financial and administrative services, approved the porch and ramp, as well as the fire suppression system changes at its Aug. 18 meeting.

    Members approved awarding $62,000 to Brivar Construction Co. to demolish the existing porch and ramp and replace the main stairs. The design, engineering and installation of the fire suppression system for $90,000 also were approved.

    Kowalewski was directed to seek bids on the kitchen renovation, as well as the installation of new water service for the council to approve. An earlier estimate for the kitchen was for $57,000.

    Emma Jean Woodyard, executive director of the Downriver Council for the Arts, said that right now the building is in a cleanup, fixup mode.

    “It’s a great partnership,” said Woodyard. “The city owns the building and the Downriver Council for the Arts will manage it.”

    The building will contain studios, galleries, classrooms and meeting spaces.

    “The third-floor theatre will require a different plan,” Woodyard said. “We’re not doing much at this time.”

    This summer Roosevelt High School used the building to perform “Godspell.” The Trenton-based Downriver Youth Performing Arts Center used the building for rehearsal space.

    Kitchen updates, plaster, lighting and room divisions are under way. January 2010 is the tentative move-in date. What officials call a much-needed elevator installation reportedly is well under way, and room divisions are needed as well.

    For more information about the renovation and art council events, visit their web site at www.downriverarts.org.